Logo
programming4us
programming4us
programming4us
programming4us
Home
programming4us
XP
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server
programming4us
Windows Phone
 
programming4us
Windows 7

Microsoft Project 2010 : Accounting for Project Costs - Accounting for Overtime Spent on Project Tasks

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Malwarebytes Premium 3.7.1 Serial Keys (LifeTime) 2019
8/12/2014 4:20:55 AM
Overtime work isn’t defined the same way in every organization. In some organizations, overtime is considered any work totaling more than 40 hours in one week. In other organizations, overtime is considered any work beyond eight hours in one day. Overtime sometimes is calculated on a monthly basis, and other times, extra hours don’t count as overtime costs because the resources are salaried. Even within one organization, there may not be a single hard-and-fast rule about overtime. Some resources may be salaried; other resources may record overtime on a daily basis; and others may account for overtime weekly.

Because of this, Project makes no assumptions about overtime. If a resource reports that he or she has worked 10 hours in one day, Project records those 10 hours as regular work. It’s up to the project manager to determine whether two of those 10 hours are actually overtime work. After the project manager has manually changed the reported work to eight hours of regular work and two hours of overtime work, the overtime rate for the resource will apply for those two hours, and costs will be accounted for correctly.

Planning for Overtime Work and Costs

If you know that some of the work on your project will be done as overtime work, you can plan for that overtime work before it actually happens. This enables you to more accurately estimate project costs by including overtime rates for resources during the planning process.

Follow these steps to plan for overtime work in Project 2010:

1.
On the View tab, in the Task Views group, click Task Usage.

2.
On the View tab, in the Data group, click Tables and then click Work.

3.
On the left portion of the Task Usage view, click the Add New Column header and then click Overtime Work.

4.
Type the amount of overtime you want to plan for in the Overtime Work column for an italicized resource assignment, as shown in Figure 1.

Figure 1. Adding planned overtime to a resource assignment.


Overtime work is considered part of the total work for a resource assignment. If the resource assignment is set to 40 hours of work, and you add 10 hours in the Overtime Work column, the Work column will stay set to 40 hours. If you meant to indicate that those 10 hours would be in addition to the existing 40 hours, you need to adjust the Work column to add the overtime (50 hours of work). Project calculates costs as follows:

(Overtime Work × Overtime Rate) = Overtime Cost
[(Work − Overtime Work) × Standard Rate] + Overtime Cost + Fixed Costs + Costs Per Use = Cost


Recording Actual Overtime Work and Costs

As resources on your project begin work on tasks, their actual work hours will begin rolling in. As the project manager, you’ll need to be recording how much of each resource’s time is actually overtime.

To add actual overtime work to your project, follow these steps:

1.
On the View menu, in the Task Views group, click Task Usage.

2.
On the View tab, in the Data group, click Tables and then click Work.

3.
On the Format tab, in the Details group, click Add Details.

4.
In the Available fields box, click Actual Overtime Work and then press Ctrl and click Actual Work.

5.
Click Show to move the selected fields to the Show these fields box.

6.
Click Actual Work in the Show these fields box to select it and then click the up arrow button on the right side of the box to move the Actual Work field above the Actual Overtime Work field.

7.
Click OK to add these fields to the time-phased (right) portion of the Task Usage view.

8.
Scroll through the list of tasks and resource assignments to display the resource assignment that has overtime and then click the row header to select the row.

9.
On the View tab, in the Zoom group, click Zoom Selected Tasks, as shown in Figure 2.

Figure 2. Click Zoom Selected Tasks in the Zoom group on the View tab.

10.
For each resource assignment, look at the Actual Work row in the time-phased portion of the view and watch for reported work that exceeds the resource’s standard amount of work. For example, look at Figure 3. The highlighted resource normally works eight hour days, and I see 10 hours of actual work reported in one day, so I know that resource has worked some overtime on that day, according to company policy.

Figure 3. This resource normally works eight hour days, so this 10-hour day includes overtime work.

11.
Determine how much of the reported Actual Work is overtime work and subtract that from the work total. For example, if my resource reported 10 hours of work, I know that two of those hours are overtime, so I subtract 2 from 10 to get eight hours.

12.
Type the new work total, minus the overtime work, in the corresponding cell in the Actual Work row.

13.
In the corresponding Actual Overtime Work row, type the amount of overtime work that the resource reported and then press Enter. The Actual Work row will be updated to add back the overtime work.

After the actual overtime work has been correctly recorded in your project, the resource’s overtime rate will be used to calculate the overtime costs.

Other -----------------
- Microsoft Project 2010 : Accounting for Project Costs - Comparing Actual Cost and Work Values with the Project Budget
- Microsoft Project 2010 : Creating a Budget for Your Project (part 2) - Adding Values to Budget Resources, Pairing Resources with Budgets
- Microsoft Project 2010 : Creating a Budget for Your Project (part 1) - Creating and Assigning Budget Resources
- Microsoft Access 2010 : Enhancing the Queries That You Build - Ordering Query Results, Refining a Query by Using Criteria
- Microsoft Access 2010 : Enhancing the Queries That You Build - Everything You Need to Know About Query Basics
- Using the Windows 7 Libraries : USING THE EXPLORER BROWSER CONTROL (part 2)
- Using the Windows 7 Libraries : USING THE EXPLORER BROWSER CONTROL (part 1) - Adding the Explorer Browser to Your Toolbox , Configuring the Explorer Browser Example
- Using the Windows 7 Libraries : CONSIDERING USER-DEFINED COLLECTIONS
- Using the Windows 7 Libraries : USING NON-FILESYSTEM CONTAINERS
- Using the Windows 7 Libraries : WORKING WITH KNOWN FOLDERS
 
 
Top 10
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
 
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server