Logo
programming4us
programming4us
programming4us
programming4us
Home
programming4us
XP
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server
programming4us
Windows Phone
 
programming4us
Windows 7

Microsoft Project 2010 : Using the Resource Fields to Define Resource Details (part 2) - Using the Max Units and Resource Availability Table to Specify Resource Availability

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Malwarebytes Premium 3.7.1 Serial Keys (LifeTime) 2019
8/22/2012 3:37:39 PM

Using the Max Units and Resource Availability Table to Specify Resource Availability

Use the Max Units field to enter the maximum number of units that can currently be assigned to tasks at any one time. Project uses the Max Units field to determine when the resource is overallocated (when more units of the resource have been assigned than are available) and when leveling resources.

For instance, suppose that Greg’s Max Units field shows 80%. That means that Greg is available to spend up to 80% of his working time on tasks in your project. If you assign Greg to spend 30% of his time on one task and 60% of his time on another task, and if the scheduled dates for those two tasks overlap, you will have assigned 90% of Greg’s time during the period of the overlap. Because this is more than the Max Units of 80%, Project calculates that the resource is overallocated; the resource name turns red in the Resource Sheet view and displays a symbol in the Indicator field to flag the overallocated resource.

You can format the Max Units field as a percentage or as a decimal. The default is the percentage format. You can change the format for the Max Units field in the Options dialog box by following these steps:

1.
On the File tab, select Options.

2.
In the Options dialog box, select the Schedule tab.

3.
Use the drop-down list in the Show Assignment Units as A box and select either Percentage or Decimal.

Project applies a default Max Units of 100% (or 1 in decimal format) when you create a resource. However, you can change the value to anything between 0% and 6,000,000,000% (between 0 and 60,000,000 in decimal format). For a single-unit resource, the default value of 100% means that this resource is available to work 100% of the hours on its calendar on this project. It can also signify that the resource is fully dedicated (100%) to complete the assigned task during the defined period. If you are grouping resources into a group resource, you enter a greater value than 100%. Thus, if you have two full-time movers in a Movers resource, you can enter 200% (or 2 in decimal format).

Note

There is no Max Units value for material or cost resources. Project assumes that you will acquire as many units as you have assigned.


A resource may have some variability concerning its actual availability. For instance, sometimes a resource is not hired until after the project starts, so up until that date, its Max Units remains 0%. On the reverse side, a resource might leave the company before the project is completed, so after his or her last day with the company, the Max Units field will be 0%. At all other times, the resource availability may vary from 0 to 100% for very specific reasons during very specific times.

You might also intend to add more units of the resource over the duration of the project. In this case, you need to record the dates when the additional units would come on board using the Resource Availability table.

You can find the Resource Availability table on the General tab of the Resource Information dialog box. Use this table to define the time periods and the max units for each time period . The default values for both the Available From and Available To columns in the Resource Availability table are NA (not applicable), and the default value in the Units (Max Units) field is 100%. The NA value means from the earliest possible date (Jan. 1, 1984) and latest available date (Dec. 31, 2049), respectively. Figure 2 shows that the Movers resource will not start work until 1/3/2011, even though the project starts earlier, and will be available until 4/1/2011 per the contract agreement, even though the project still continues after 4/1.

Figure 2. The Resource Information dialog box’s Resource Availability table is used to track the changes in resource availability down to specific date ranges and units.

The Max Units field on the Resource Sheet view and on the Resource Form view displays the Units value from the Resource Availability table for the current date. The current date is normally the computer’s current date, but it can be any date you choose to enter into the Current Date field in the Project Information dialog box. If you look at the Max Units field for Movers on the Resource Sheet view on any date prior to 1/3/2011, the value will be 0%, because the movers are unavailable to work on the project before 1/3/2011 according to the Available From column. After 1/3/2011, it will be 200%.

Tip

Be sure that the dates in the Resource Availability table are in sequential order and that you leave no gaps in the dates from one row to the next. If you have an Available From date that is more than one day later than the Available To date on the previous row, Project assumes the resource is unavailable between those dates and uses 0% as the Max Units value for the dates in the gap.


When Project examines this schedule to see if the Movers resource is overallocated, it shows the overallocated indicator if the total assignments for the Movers resource exceed 200% on any date outside the date range of 1/3/2011–4/1/2011.

To change the Resource Availability table for a resource, follow these steps:

1.
In a view that shows resource names, such as the Resource Sheet view, select the resource and click the Resource Information button on the Resource tab of the Ribbon. You can also simply double-click the resource name.

Caution

When entering dates in the Available From and Available To columns, be aware that those dates are fixed unless you change them. If a resource’s availability dates change, be sure to correct the changes in the Resource Availability table.

2.
Click the General tab, if it is not displayed.

3.
Click the cell for the date you want to change under the Available From or Available To column. You can either type in the date or use the drop-down arrow to select the date.

4.
Enter the max units for that row’s date range in the Units column.

5.
After all entries are completed, click OK to save the changes. Or you can click Cancel to close the dialog box without saving any changes.

Note

The Resource Availability table is not available for material resources, which are assumed to be always available to the project.

Other -----------------
- Microsoft Project 2010 : Defining Resource Information Using the Resource Information Dialog Box
- Your Life in Sync—Windows 7 and Live Services : Going Online and Learning about Windows Live
- Working with Ultra-Mobile PCs : A Tour of the UMPC Software
- Microsoft Access 2010 : Finding the Largest and Smallest Values in a Field by Using a Query
- Microsoft Access 2010 : Creating Queries - Creating a Crosstab Query
- Microsoft Access 2010 : Creating Queries - Writing Query Results to a New Table, Creating an Update Query
- Microsoft Excel 2010 : Defining Multiple Alternative Data Sets
- Microsoft Excel 2010 : Defining an Alternative Data Set
- Tools for Troubleshooting (part 9) - TCPView, Telnet Client
- Tools for Troubleshooting (part 8) - Route & Task Manager
 
 
Top 10
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
 
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server