Customizing Microsoft Project 2010 : Creating Custom Fields

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Malwarebytes Premium 3.7.1 Serial Keys (LifeTime) 2019
11/8/2011 9:18:47 AM
Custom fields can be used to add information to your project that isn’t captured using the default fields that come with Project 2010. That information might be specific to your project, your team, or your organization, for example.

To create a custom field in your project, follow these steps:

1.
On the Project tab, in the Properties group, click Custom Fields.

2.
Choose whether you are customizing a Task or Resource field, as shown in Figure 1.



Figure 1. Choose from Task, Resource, or Project in the highlighted portion of the Custom Fields dialog box.


If you are connected to Project Server, you can also customize project fields using Project Web App.


3.
In the Type list, click the type of data you plan to enter in the field you are customizing.

4.
In the Field box, click the name of the field you are customizing. If the field has a friendly name followed by the original, generic name in parentheses, it is most likely already being used.

5.
Click Rename, type a new friendly name for the field in the New name for box, and then click OK.

6.
Under Custom Attributes, if you just want to be able to enter data in the field, leave it set to None. However, if you want to control the data, choose one of the following options:

  • Lookup— If you want to choose a value from a list, click Lookup, type each of the list values in the Value column, choose any other options that may make sense for your list, and then click Close.

  • Formula— If you want to calculate the value in the field using dates or other project data, click Formula. Formulas can only be used to calculate data for a single task or resource. Formulas cannot reference the values of fields in other tasks or resources. For example, if you create a formula that displays or acts upon the Start Date field, that formula will only be using the start date for the corresponding task.

Office.com has a great resource to help you build your own formulas. “Project functions for custom fields” is available at http://office.microsoft.com/project-help/HP010080956.aspx. It provides a list of functions, including descriptions and examples, that you can use within formulas for custom fields in Project 2010.


7.
Under Calculation for task and group summary rows, choose one of the following options:

  • None— Click None if you don’t want the field rolled up to the task and group summary levels.

  • Rollup— Click Rollup and choose how you want the rollup calculated if you want the field values summarized at the task and group summary levels.

  • Use formula— Click Use formula if you selected Formula under Custom attributes and you want to use that formula for the rollup values for the field you’re customizing.

8.
Under Calculation for assignment rows, click None if you don’t want the values in this custom field to be spread across assignments or click Roll down unless manually entered if you want the values spread evenly across each assignment. If you choose Roll down unless manually entered, the values will be evenly distributed, but you’ll still be able to manually enter data to refine the distribution.

9.
Under Values to display, click Data to display the data “as is” or click Graphical Indicators to display an icon based on the data entered in the field. For example, you can assign red, yellow, and green icons to different status descriptors to provide a visual health indicator.

10.
Click OK to save your custom field.

Other -----------------
- Microsoft Project 2010 : Sharing Data with Others
- Designing a Zero-Touch Deployment (part 2) - Deploying ZTI Task Sequences to Target Computers
- Designing a Zero-Touch Deployment (part 1) - Using System Center Configuration Manager & Creating Task Sequences Using SCCM
- Troubleshooting and Recovering from Disaster : Using the Windows Recovery Environment
- Troubleshooting and Recovering from Disaster : Getting Help with the Problem Steps Recorder
- Microsoft OneOnte 2010 : Tagging Notes for Follow Up
- Microsoft OneOnte 2010 : Moving, Copying, and Merging Pages and Sections
- Microsoft Project 2010 : Reporting on Your Project (part 1) - Generating and Customizing a Basic Report
- Microsoft Project 2010 : Reporting on Your Project (part 1) - Generating and Customizing a Visual Report
- Zipping and Packing Files, File and Folder Security
 
 
Top 10
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
 
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server