Logo
programming4us
programming4us
programming4us
programming4us
Home
programming4us
XP
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server
programming4us
Windows Phone
 
programming4us
Windows 7

Microsoft Project 2010 : Setting Up a Project Budget - Reducing Project Costs

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Malwarebytes Premium 3.7.1 Serial Keys (LifeTime) 2019
12/25/2012 5:56:43 PM

If your costs are coming out to $110,000 when your maximum is $95,000, you have to figure out how to trim $15,000 from your planned project costs or heads will roll—most likely yours. How does one go about cutting thousands of dollars from a project? Answer: very carefully.

First, look at your cost assumptions to make sure mistakes haven't sent project costs into the stratosphere. If you're lucky, you can correct the misplaced zero you find and everything becomes hunky-dory. The next line of defense is to reschedule tasks to reduce costs. You can also examine resource assignments to look for ways to cut costs.

This section discusses each of these cost-cutting techniques. However, if these methods aren't enough to solve your budget crisis, it's time to take a hard look at the budget itself and propose a change to the project budget, scope, or schedule.

1. Checking for Cost Errors

When your TV suddenly doesn't turn on, or you can't get the channel that's showing world championship bass fishing, you probably don't schedule a technician service call right away. You poke around, hit buttons on the remote, turn things off and on, and see if the picture comes back. If you're really thinking straight, the very first thing you check is whether your dog unplugged the TV cables or power cord again.

The same troubleshooting principle applies when planned project costs don't jibe with your project budget. Don't assume that the project is really $15,000 over budget just yet. Look for errors, starting with the simple, most obvious things first. In this section, you learn how to systematically scan your project plan for mistakes in cost values or calculations.

Here are cost-related items to check, and where to look for them:

  • Task durations. Review task durations for any that approach the length of geologic eras. Durations affect cost because Project multiplies duration by rates to calculate cost.

  • Cost per use. In the Resource Sheet, look for values in the Cost Per Use column . Remember that a cost per use is levied for each task a resource is assigned to. For example, suppose a crane costs $5,000 to get it on-site. If you apply the $5,000 as cost per use, and then assign the crane to six tasks, your project cost includes $30,000 for crane setup instead of only $5,000. In this situation, a cost resource for getting the crane on-site makes more sense than cost per use. On the other hand, a Dumpster may cost $5 a day to have on-site as well as $450 each time you empty it. If a resource has a standard rate combined with a cost per use, make sure they're both legitimate.

  • Resource rates. Also in the Resource Sheet, review the rates you've assigned to human, equipment, and material resources. If you have a lot of resources, consider sorting by standard rate so that excessively high or low rates stand out. (For example, if a janitor comes out higher than your information architect, someone's standard rate is off.) Click the down arrow to the right of the Std. Rate column heading and then, on the drop-down menu, choose Sort Descending. To return the view to its normal order, choose View→Data→Sort→"by ID".

  • Planned assignment costs. Apply the Cost table to the Resource Sheet, and then check your resources' costs on their assignments. The Cost field shows the total planned cost for a resource for all tasks it's assigned to. To see the resources that run the tab up the most, sort the view by the Cost field (click the down arrow to the right of the Cost column heading and then, on the drop-down menu, choose Sort Largest to Smallest). Then you can focus on ways to reduce the costs for those resources.

  • Cost resource amounts. To easily review cost resource amounts, display the Resource Usage view, apply the Cost table, and then group the view by resource type (click the down arrow to the right of the Resource Name column heading and then, on the drop-down menu, choose "Group by"→Resource Type). Scroll down to the Type: Cost grouping, and the result looks similar to Figure 11-18. To return the view to its normal ungrouped arrangement, choose the down arrow to the right of the Resource Name column heading and then, on the drop-down menu, choose No Group.

  • Fixed costs for tasks. In the Gantt Chart view, check any fixed costs for tasks to see if they have one or two zeroes too many. Apply the Cost table to the view, and then sort by the Fixed Cost field. (Click the down arrow to the right of the Fixed Cost column heading and then, on the drop-down menu, choose Sort Largest to Smallest to show the highest fixed costs at the top of the view.) Make sure you're not using a fixed cost and a cost resource for the same expense on the same task.

After you've thoroughly reviewed resource cost assumptions, as well as task information that affects cost, be sure to take a closer look at the budget itself. Rather than being carved into stone by lightning bolts from on high, the budget is prepared by a human being like you. Check the assumptions in the budget, and make sure someone hasn't made any outlandish mistakes there.

Figure 1. When you apply the Cost table to the Resource Usage view, and then group the view by resource type, you see all the cost resources together, the tasks they're assigned to, and the amounts designated for each assignment. If you find an error, you can change it right there in the assignment row.


2. Adjusting the Schedule

If your planned costs and the budget still don't see eye-to-eye after you've corrected cost mistakes, it's time for Plan B: adjusting the schedule. Here are some ways you can adjust the schedule to reduce costs:

  • Task durations, part deux. You've already scrutinized task durations looking for possible errors. Now see if there's any way to realistically shorten durations and still get the job done. Sometimes shortening tasks actually costs more,.

    In the Gantt Chart view, make sure the Entry table is visible. You can run down the tasks in order or sort the schedule by duration to cherry-pick the longest durations for your scrutiny. To show the longest durations at the top of the view, choose View→Data→Sort→Sort By, and then, in the "Sort by" box, choose Duration and select the Descending option. Turn off the "Keep outline structure" checkbox, and then click Sort. To hide summary tasks, choose Format→Show/Hide and turn off the Summary Tasks checkbox.

  • Task relationships. Sometimes by linking tasks more aggressively , you can shorten the time you have to pay resources while they wait for their next task to begin. To most easily review task relationships, in a Gantt Chart view, look at the Gantt bars.

  • Date constraints. Any constraints other than As Soon As Possible (or As Late As Possible for a project scheduled from the finish date) are worth a second look . If you have a task with a Must Finish On or Start No Earlier Than date constraint applied, resources may be waiting in limbo unnecessarily for the right time to work on tasks. Removing that limbo time can help you cut costs. Add the Constraint Type and Constraint Date fields to a table, and then sort or group by Constraint Type.

3. Adjusting Assignments

If you've adjusted the schedule to optimize your costs but you still have more belt tightening to do, try adjusting resource assignments. Here are a few strategies to try:

  • Replace expensive resources with cheaper ones. Consider having your more experienced (and probably more expensive) resources mentor your less costly resources for a short time on tasks, rather than working the entire task. Or use cheaper in-house—perhaps borrowed—resources, rather than more expensive outside consultants. On the other hand, sometimes hiring temporary contract labor is cheaper than using your in-house employees.

  • Do away with overtime. If your current schedule involves overtime, see if you can adjust assignments to eliminate overtime (on resources that cost more for overtime, of course).

4. Rethinking Your Project Budget

If your best efforts on project costs still don't line them up with the project budget, then it's time for renegotiation. You've checked and rechecked that your costs reflect the project reality—as you know it so far. The next step is talking to the customer, the project sponsor, or whichever head honcho holds the purse strings. There are two choices in this situation.

  • Get a bigger budget. The first and usually most difficult option you may consider is trying to get more money appropriated for the project.

  • Cut back on project scope or quality. Cutting the number of tasks, for example, a particular phase, or reducing quality objectives can cut costs—but only if all the stakeholders agree. 

Other -----------------
- Microsoft PowerPoint 2010 : Incorporating Motion Video - Placing a Video on a Slide
- Microsoft PowerPoint 2010 : Incorporating Motion Video - Understanding Video Types
- Microsoft Excel 2010 : Using Formulas - Using Names To Simplify References, Inserting Formulas into Tables
- Microsoft Excel 2010 : Using Formulas - Copying a Formula, Formula Operators
- Microsoft Word 2010 : Proofing a Document - Finding and Replacing Text
- Microsoft Word 2010 : Checking Your Spelling and Grammar
- Microsoft Visio 2010 : Finding and Managing Shapes (part 3)
- Microsoft Visio 2010 : Finding and Managing Shapes (part 2) - Searching for Shapes
- Microsoft Visio 2010 : Finding and Managing Shapes (part 1) - Navigating the Shapes Window, Opening Other Stencils
- Managing Windows 7 : Adding or Deleting User Accounts
 
 
Top 10
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
 
programming4us
Windows Vista
programming4us
Windows 7
programming4us
Windows Azure
programming4us
Windows Server